Anticipated Project Schedule
| Select Project Artist |
Winter 2007 |
Completed |
| Design |
Spring - Fall 2007 |
Completed |
| Public Meeting #1 |
Summer 2007 |
Completed |
| Public Meeting #2 |
Fall 2007 |
Completed |
| Final Design |
Fall 2007 - Summer 2008 |
Completed |
| Public Meeting #3 |
Summer 2008 |
Completed |
| Right-of-Way Acquisition |
Spring 2008 – Fall 2009 (Estimated 18-month duration) |
|
| Construction |
Fall 2009 - Summer 2011
(Estimated 18-month duration) |
Future |
|
Design Phase
We are currently in the final design phase. This phase includes:
– Collecting data on the existing conditions of the area
– Developing designs for roadways, sidewalks,
gateway features, gathering areas,
and other streetscape elements
– Determining locations for streetscape elements
– Developing preliminary cost estimates
– Establishing a preliminary construction phasing schedule
– Right-of-Way Acquisition
The design team has reviewed, evaluated, and refined concepts in the master plan to develop a streetscape design. The results of the traffic analysis, surveys, planning and design work, additional research, and public input will be reflected in the design. After the design phase, the project will move forward with
permitting and project construction.
Click below to view the Streetscape Communications and Stakeholder Involvement Plan, which includes the anticipated schedule for public outreach activities.

|
|